Route 600 is closed at U.S. 15/29 to May 2027, with the detour on Vint Hill Road. No full closures in Linton Hall; Devlin Road widening runs to spring 2028.

Last checked Nov. 11, 2026. This page is refreshed weekly. Sources: Prince William County Current Road Projects, Virginia 511, VDOT news releases and VDOT.

Linton Hall’s main roads, including Nokesville Road (Route 28), Prince William Parkway (Route 234), Vint Hill Road (Route 215) and Devlin Road (Route 621), are numbered state routes, and the Virginia Department of Transportation handles their upkeep. Prince William County designs and builds many of the bigger improvements on them. Here is what is under way or coming.

Who to call

  • Live closures and traffic: 511 Virginia or dial 511
  • Potholes, signs, signals and debris on state roads: VDOT Customer Service Center, 800-367-7623 (800-FOR-ROAD), 24 hours, or online
  • County road projects: Department of Transportation, 703-792-6825 (TTY 711), weekdays 8:30 a.m. to 4:30 p.m.
  • Crash or hazard needing police: 911; non-emergency 703-792-6500

This week

As of Wednesday, Nov. 11, VDOT’s work zone feed on 511 lists no full road closures inside Linton Hall. The work closest to home:

  • Route 600 (Broad Run Church Road) at U.S. 15/29 (Lee Highway), Fauquier County: a short stretch of Route 600 is closed to through traffic at the approach to Lee Highway while crews add a left-turn lane. VDOT closed it Oct. 21 and expects the detour to be lifted by May 9, 2027; the 511 work zone entry runs to July 7, 2027. The detour, about five miles, uses U.S. 15/29, Vint Hill Road (Route 215) and Broad Run Church Road, so expect more traffic on Vint Hill Road. Private driveways stay open. The $1.8 million project’s contractor is J.L. Kent & Sons, according to VDOT’s Culpeper District release.
  • Devlin Road (Route 621): the county’s widening between University Boulevard and Jennell Drive, near Chris Yung Elementary School, continues. 511 showed no posted lane closure on Devlin Road at the time of this check; work zones can appear at short notice.

The Route 234 overnight paving at I-66 and the U.S. 29 night lane closures near Gainesville listed here Oct. 29 no longer appear on 511. VDOT’s Northern Virginia news releases from Oct. 29 to Nov. 11 announced no closures in Linton Hall, Bristow, Gainesville or Manassas. Check 511 before you drive; it updates around the clock.

County projects in and near Linton Hall

All are in the Brentsville Magisterial District, from the county’s Current Road Projects page.

Project What it does Schedule
Devlin Road widening Widens Devlin Road (Route 621) to a four-lane divided road for about 3,000 feet from University Boulevard to Jennell Drive, with a sidewalk, a shared-use path and a new signal at Fog Light Way and Pike Branch Way Construction began fall 2025; ends spring 2028
Rollins Ford Road roundabouts Two roundabouts on Rollins Ford Road, at Song Sparrow Drive and Yellow Hammer Drive, and at Estate Manor Drive County lists construction as beginning fall 2026 and ending spring 2028; no start date or closure announced as of Nov. 11
Sudley Manor Drive interchange Improvements at Prince William Parkway (Route 234) and Sudley Manor Drive, with changes at Wellington Road Design-build contract began July 2026; runs to December 2030
University Boulevard extension Extends University Boulevard from Devlin Road to Wellington Road as a four-lane road with a sidewalk and a 10-foot shared-use path Design-build contract began July 2026; runs to fall 2028
Sudley Manor Drive sidewalk A 5-foot sidewalk on the north side of Sudley Manor Drive with a 4-foot buffer Listed by the county; dates not yet posted

Devlin Road: expect lane shifts and work zones between University Boulevard and Jennell Drive near Chris Yung Elementary School and the Fog Light Way neighborhoods until 2028.

Sudley Manor Drive interchange: the county posted public information documents dated Oct. 7, 2026, and the meeting presentation, on the project page.

Rollins Ford Road: the county held a public hearing on the roundabouts in April 2026 and has not yet announced when crews start; the hearing brochure shows the designs.

The county also lists a separate Route 234 and Brentsville Road interchange project south of Linton Hall.

Other state road work

VDOT is studying the widening of Route 28 (Centreville Road) from Liberia Avenue in Manassas to just south of Compton Road in Fairfax County, a corridor many Linton Hall commuters use. It is a study, not construction: VDOT plans a public meeting on preliminary alternatives in spring 2027 and final recommendations in fall 2027, according to its project page.

How to stay ahead of closures

  • 511 Virginia: live map of incidents, work zones and cameras; the 511 app; or dial 511.
  • Prince William County alerts, which include road closures.

What this means for you

Drivers heading to U.S. 15/29 by Broad Run Church Road should use the Vint Hill Road detour until spring 2027. Allow extra time on Devlin Road until spring 2028. Rollins Ford Road drivers should watch for the county’s construction notice for the roundabouts, which it still lists for fall 2026. Related guides: getting around Linton Hall, who to call and things to do.

Frequently asked questions

When will the Devlin Road widening in Bristow be finished?

Prince William County expects to finish widening Devlin Road to four lanes between University Boulevard and Jennell Drive in spring 2028. Construction began in fall 2025.

Where can I check road closures near Linton Hall?

Virginia’s 511 site at 511.vdot.virginia.gov, or call 511, shows live incidents, lane closures and work zones on state roads, including Linton Hall Road, Nokesville Road and Prince William Parkway.

Who fixes potholes on Linton Hall Road?

VDOT maintains the state roads in Prince William County. Report potholes and other problems to the VDOT Customer Service Center at 800-367-7623 or online at my.vdot.virginia.gov.

What is being built at Prince William Parkway and Sudley Manor Drive?

An interchange. The county began a design-build contract in July 2026 for improvements at Route 234 and Sudley Manor Drive, including changes at the Wellington Road intersection. The county lists the contract as running to December 2030.