County supervisors approved a second drive-through lane for the Virginia Gateway Chick-fil-A in Gainesville on Nov. 17. No construction date has been set.

Updated Nov. 18: The Board of County Supervisors approved the permit Tuesday, Nov. 17. Details of the vote are below.

The Chick-fil-A at Virginia Gateway in Gainesville can add a second drive-through lane. The Prince William Board of County Supervisors approved the request Tuesday, Nov. 17, after a public hearing.

The restaurant sits by the northern end of Linton Hall Road, about five miles northwest of Linton Hall. It operates one drive-through lane today.

County planning staff and the Planning Commission had both recommended approval. The case is Special Use Permit #SUP2025-00031, and its full file is item 8-B on the board’s Nov. 17 agenda.

What the restaurant is asking for

The request would amend the restaurant’s 2008 special use permit. According to the county staff report, it would:

  • raise the number of drive-through lanes allowed from one to two
  • add new canopies over the order point and the food delivery area
  • reduce the parking required on site
  • allow related changes to signs

The project area covers about 1 acre at 5015 and 5153 Wellington Road. Staff place it about 330 feet north of the intersection of Wellington Road and Gateway Promenade Place. The land is zoned B-1, General Business, and lies in the Brentsville Magisterial District.

Traffic and parking conditions

The drive-through backup is the issue most drivers will care about. The draft conditions, dated Sept. 22, deal with it in several ways.

  • One-way loop. Cars in the drive-through must circulate one way, counterclockwise.
  • No new driveways onto main roads. Direct access onto Wellington Road and Linton Hall Road is prohibited.
  • Fire lanes kept clear. The applicant must make sure its customers’ cars do not block fire lanes or the nearby roads.
  • A traffic plan if lines spill over. If cars back up onto public roads, fire lanes or the nearby road network for more than 15 minutes in a row, the county transportation department can demand a traffic management plan within 30 days.

In the first year after the second lane opens, the county will only ask for that plan if it sees such spillover more than three times in a single week.

On parking, the plan provides 65% of the required spaces on site. The other 35% would come from a shared parking agreement with the Virginia Gateway shopping center. County rules allow up to half of the required parking on an adjacent property within 500 feet, so staff recommended the waiver.

Staff said the extra lane “will not have significant impact on existing levels of service” on nearby roads. The staff report does not include a traffic count for the restaurant.

How the vote went

The board heard the case alongside five other land use cases, items 8-A through 8-F, and closed all six hearings together. No speaker addressed the Chick-fil-A request. The board then took its votes, and the result was announced as unanimous. That account comes from the county’s video record of the Nov. 17 meeting. The county’s written summary of the board’s actions had not been posted by Wednesday.

The Planning Commission held its public hearing Sept. 16. It voted 8-0 to recommend approval, according to its resolution, Res. No. 26-099, which is attached to the board item.

The county mailed notice to property owners within 500 feet. As of the staff report, the Planning Office had received no verbal or written comments and was “not aware of any opposition.”

With the permit approved, the applicant must file a site plan within a year. It then has up to five years from final site plan approval to start using the second lane.

What it means for you

  • If you use this drive-through, a second lane could shorten the wait, but construction comes first, and no start date has been set.
  • Nothing changes yet. The applicant has a year to file a site plan, and up to five years after that plan is approved to open the second lane.
  • If you drive Linton Hall Road or Wellington Road, the traffic conditions above are the county’s tool if drive-through lines spill onto the road.

The full agenda remains on the county’s Granicus page for the Nov. 17 meeting. Other local land use cases are on our building permits and zoning page, and current lane closures are on our road construction and closures page.