Four trail gaps near Linton Hall and a Broad Run paddling route are top priorities in the county's new trails plan. No money comes with it yet.
Prince William County has a new trails master plan. Several of its highest-priority gaps sit along Broad Run, around Linton Hall’s neighborhoods.
The plan is called Pathways 2035. The Board of County Supervisors took it up at its Oct. 20 meeting, and the county announced Oct. 28 that the board had adopted it. It ranks every unbuilt trail gap in the county into three tiers. Tier 1 is the top priority.
The plan does not pay for anything. The county said adoption “does not authorize construction or funding for individual projects.” Each project will need its own funding decision later.
The top-tier trail gaps closest to Linton Hall
The plan’s Brentsville District list includes these Tier 1 recreational segments, according to Appendix B of the plan in the Oct. 20 board agenda:
- Rocky Branch Greenway, 2 miles: from Bridlewood Park to Broad Run at Hunting Cove
- Broad Run Greenway, 0.69 miles: the stretch the plan labels “Victory Lakes to Avanti”
- Devlin transmission line, 0.43 miles: an extension from Hunting Cove to Linton Hall
- Broad Run Greenway, 0.73 miles: a segment labeled “Bristow Campus”
The Rocky Branch corridor starts at the county’s undeveloped Bridlewood-Rocky Branch Park property, just north of Rollins Ford Road. It ends at Broad Run near the Hunting Cove Place entrance to Broad Run Linear Park, the plan says.
Two of those segments are “planned,” which generally means the county already has the land, an easement or an approved study. The other two are “proposed,” which means no design, study or land work has been done yet.
The plan’s district list puts other local links lower. These are Tier 2:
- the Broad Run Greenway on the west side, which the plan labels “Linton Hall to YFT” (1.81 miles)
- the Devlin transmission line from Linton Hall to Wellington (two segments, 1.56 miles in all)
- the Hunting Cove trailhead connector to Linton Hall Road (0.06 miles)
Roadside paths: Wellington Road leads, Linton Hall roads wait
The plan also ranks gaps in paved paths along roads. Four Brentsville District road segments made Tier 1:
| Road | Type | Miles | Section | Cost estimate |
|---|---|---|---|---|
| Bristow Road | Paved shoulder | 9.10 | Nokesville Road to Independent Hill Drive | Varies |
| Wellington Road | Shared-use path | 5.57 | University Boulevard to Godwin Drive | $42.0 million to $56.0 million |
| Hornbaker Road | Shared-use path | 1.82 | Wellington Road to Thomasson Barn Way | $13.7 million to $18.3 million |
| Prince William Parkway | Shared-use path | 1.65 | Sudley Manor Drive to Innovation Drive connector | $12.4 million to $16.6 million |
Paths on Linton Hall’s own main roads rank lower. A 3.5-mile path on Vint Hill Road, from Rollins Ford Road to Fitzgerald Way, is Tier 2, at an estimated $26.4 million to $35.2 million. Paths on Glenkirk Road, Rollins Ford Road, Devlin Road and Linton Hall Road between U.S. 29 and Gateway Center Drive are Tier 3.
The full ranked lists are in Appendices A and B of the plan.
A paddling route on Broad Run
The plan is the county’s first full look at “blueways,” or water trails for canoes and kayaks. It names Broad Run as the place to start.
The plan recommends studying a paddling trail on Broad Run from just below the Lake Manassas dam to Nokesville Road, which is Route 28. That stretch runs past the county’s 264-acre Broad Run Linear Park. The park runs from Hunting Cove Place in Kingsbrooke to the Sowder Shopping Center at Route 28. Braemar, Pembrooke (Victory Lakes) and Saybrooke sit along it, the plan says.
There is no public launch on that section today, the plan says. It recommends checking whether the park’s land could provide one. The county’s target is a launch every 2 to 3 miles.
The countywide picture
The county counted these unbuilt gaps:
- 291 miles of active mobility trails, such as shared-use paths, bike lanes and paved shoulders
- 118 miles of recreational trails, both paved and natural surface
Tier 1 covers 42 road segments of about 76 miles and 44 recreational segments of about 54 miles, the county said. It said not all Tier 1 projects are expected to be finished within the plan’s time frame.
Along the whole Broad Run Greenway, the plan counts 5.9 miles of trail open today. It lists 6.7 miles where the county has easements and 8.7 miles still only proposed.
The plan grew out of an online survey, two in-person planning sessions and input from the county’s Trails and Blueways Council. The council endorsed it 12-0 on Sept. 22 and asked the board for “regular funding of the plan.”
What it means for you
- Nothing changes on the ground yet. No trail is funded or scheduled by this plan.
- The ranking matters at budget time. Tier 1 segments are the ones staff will put forward first when the county builds its capital budget.
- Easements are voluntary. The plan says trail easements on private land are “always at the discretion of the property owner.”
- Today’s trails are still open. Our guides to parks and trails and walking and biking trails list what you can use now. Road work that affects these routes is on our road construction page.
The Devlin Road widening is a separate county project. Our Devlin Road story has the latest.